Abstract:An introduction to the commissioning preparation,commissioning process,pre‑commissioning inspection,commissioning and operation test of VFD cabinets and VFD motors, and air conditioning unit power‑on single‑machine test run of the control system of VFD air conditioning units of the central air conditioning system in Terminal T1 of Chengdu Tianfu International Airport is made, and matters needing attention in commissioning of VFD control system of air conditioning units are summarized.
Key words:central air conditioning system;combined air conditioning unit;filter;frequency converter;pre‑commissioning inspection;VFD control system commissioning;single machine test run of air conditioning unit;power‑on test
摘 要:介绍成都天府国际机场T1航站楼中央空调系统变频空调机组控制系统的调试准备工作及调试流程、调试前的检查、变频柜及变频电机调试运行试验、空调机组通电单机试运行,总结空调机组变频控制系统调试的注意事项。
关键词:中央空调系统;组合式空调机组;滤波器;变频器;调试前的检查;变频控制系统调试;空调机组单机试运行;通电试验